Yuchai Power Four major Projects Finished
2013-07-12
Four Yuchai Power major peojects finished on June 28, 2013, and the ceremony was held in Yuchai Power. The four projects are gas engine machine production base, 6C diesel enigne production line, national 4 engines, and national innovation center, and all the projects are in Yuchai Industrial park.
Four
Yuchai Power major peojects finished on June 28, 2013, and the ceremony was held in Yuchai Power. The four projects are gas engine machine production base, 6C diesel enigne production line, national 4 engines, and national innovation center, and all the projects are in Yuchai Industrial park.
The gas engine machine production base is composed of 5000 m2 CNG gas eninge production plant, 4200 m2 heavy-duty engine production plant amd 13500 m2 parts storage. The annual production capacity will amount to 10000 units.
6C diesel enigne production line started to build in 2010, and it reconstructed original assets and build 6C engine production lines. 6C diesel engine testing lines to meet increasing needs.